Thematic Area |
Energy and Environment |
|
Location |
Jamaica |
|
Start Date |
July 2009 |
|
Duration |
2009-2011 |
|
Funding Amount |
US$85,000 |
|
Source of Funding |
MPF |
|
Executing Agency |
|
|
Implementing Agencies |
|
|
Status |
Operationally Closed |
|
Objectives |
|
| To prepare the document which describes the proposed institutional arrangements and budgets for the preparation of an HCFC Phase-out Management Plan (HPMP) for Jamaica | |
|
Expected Results |
|
| HCFC Phase-out Management Plan (HPMP) for Jamaica | |
|
Profile: |
|
|
This document describes the proposed institutional arrangements and budgets for the preparation of an HCFC Phase-out Management Plan (HPMP) for Jamaica, which has assigned to UNDP, the responsibility of preparing the HPMP. Such arrangements would need: a) To reflect national context and priorities, national policies and country-drivenness and consequently would need the agreement of Jamaica to the proposals contained herein; b) To facilitate seamless application of the proposed arrangements to the implementation stage of the HPMP to follow, once it is approved; c) To draw upon the lessons learnt from functioning of institutional arrangements and operational mechanisms employed for the ongoing portfolio of projects under the Montreal Protocol and to the extent possible integrate existing infrastructures; |
|
|
Delivery in: |
|
|
2009 Allocation: US$47,000 2009 Expenditure: US$705 2010 Allocation: US$46,295 2010 Expenditure: US$18,141 2011 Allocations: US $ 10,977 2011 Expenditures (provisional): US$ 10,000 |
|
|
Contact: |
|
|
Project Manager: Mrs. Nicol Walker
|
|
|
Downloads: |
|
|
Previous years: N/A |
|
|
Additional avaalable information: |
|
|
Useful Links: |
|
|
Publications: HCFC Phase Out Management Plan for Annex C Group I substances for Jamaica |
|